Trash moves to new pen beside Rec Center as Parks promises faster pickup

Charles Velasquez-Witosky

Trash moves to new pen beside Rec Center as Parks promises faster pickup
NYC Parks has installed new pens to collect trash in the park. Photo by Charles Velasquez-Witosky

On Oct. 15, the NYC Parks Brooklyn Borough Commissioner provided updates on trash in Sunset Park and the reopening of the Sunset Park Recreation Center over a Zoom presentation.

Regarding trash, NYC Parks has constructed a pen with plastic containers on the lawn to the right of the recreation center where the trash will be collected, rather than at the entrance to the park on Sixth Avenue and 41st Street.

Following its collection in this pen, the trash will be picked up “much faster,” per Council Member Alexa Avilés, who attended the online presentation.

Over the summer, the trash, its smell, and the rats it attracted were a major complaint among residents in the neighborhood.

Council Member Avilés said the most gratifying part of the conversation was NYC Parks admitting that the way that situation was handled was a “complete failure.”

“It’s rare you actually hear anyone admitting to a mistake like that. I was shocked but pleased that they would admit failure like that out loud,” said Avilés. “What they said was that part of the issue was that there are two kinds of collection trucks, big packers and little packers. In Sunset Park, apparently there was only a big packer, which requires a CDL to operate, and the city has a shortage of CDL drivers. But they’ve now committed to having a little packer near the park to collect the trash faster, which any employee can operate. And finally, they said our park is going to be the first park in the city to have the new containers. But I’ll believe that when I see it.”

The second half of the presentation was dedicated to updates on the recreation center, which has been closed for renovations since September 2023.

As of now, the “target opening” of the rec center is winter 2027. No exact date was given. The work that remains to be completed is: Hanging televisions to support program spaces Running electric power in various areas Installing tile floors in office spaces Installing epoxy floors throughout building Replacing door lintels and brick work Door replacement Plumbing repairs Window repairs

In addition to construction, the gym will also need to be stocked with exercise equipment. Other areas, such as the bathroom and front desk, will need to be “set up,” per the presentation slides.

The original projected end date of the project was March 2025.

Council Member Avilés has taken a tour of the in-progress rec center. She described the entrance as “restored and beautiful.”

She also explained her simultaneous understanding and frustration that the project is taking so long to complete.

“I understand because it’s a landmarked structure, it takes a long time, but opening the rec center is long overdue. So for now, we keep pushing. It’s nice the pool was able to stay operational during the work, but we want these spaces to be open,” said Avilés.